How Cigar Lake Mine slashed work order scheduling time

This global leader in uranium production optimized maintenance efficiency by streamlining work management, automating tasks, and improving visibility. With real-time material tracking and intuitive dashboards, they were able to improve operational performance while maintaining rigorous safety standards.

530+

employees and contractors benefiting from improved maintenance workflows

accent stroke

97.5%+

time reduced for scheduling work orders

accent stroke

2012

the year Cigar Lake Mine implemented Prometheus Planning & Scheduling

accent stroke

Challenge

Cameco Corporation’s Cigar Lake Mine initially aimed to implement a simple solution for printing multiple maintenance documents with SAP work orders. However, after adopting Prometheus Planning & Scheduling for SAP in 2012, they uncovered additional benefits, including enhanced material management and compliance reporting. Their key challenges included: 

  • Document collection inefficiencies – Needed a streamlined way to generate and print maintenance documents.
  • Limited visibility into job interdependencies: Required better insight into task relationships.
  • Complex workflows: Needed user-friendly tools to simplify processes.
  • Maintenance forecasting limitations: Lacked tools to predict and plan maintenance activities.
  • Strict safety, environmental, and quality standards: Required solutions that maintained regulatory compliance. 

Solutions

Since 2012, Cigar Lake has leveraged Prometheus Planning & Scheduling to enhance SAP Work Management. Key implementations include: 

  • Configurable Dashboard: Became essential for maintenance teams and operations, especially in terms of work approvals and backlog reviews, as well as for regulatory reporting.
  • Material Shopping Cart: Enabled supervisors to quickly locate and add materials to work orders in real time, while also enabling them to Improve material tracking and availability.
  • Extended Functionalities (XF) for shutdowns and turnarounds: Improved tacking of critical path tasks, in addition to the Identification of potential scheduling conflicts.

Results

The adoption of Prometheus solutions has significantly optimized planning and scheduling, leading to: 

  • Massive time savings: Scheduling 200 work orders now takes under 30 seconds instead of 20 minutes.
  • Reduced manual and repetitive tasks: Freed up time for higher-value work.
  • Improved scheduling visibility: Allowed supervisors to proactively resolve conflicts.
  • Enhanced workflow efficiency: Drag-and-drop functionality streamlined work assignments.
  • Ongoing optimization: Cigar Lake continues to explore new Prometheus capabilities with strong customer support.